EON” Fiberglass Reinforced Plastic Continuous Slot Wound Well Screens OPEN AREA (SQUARE INCHES & CENTIMETERS) AND TRANSMITTING CAPACITY (GALLONS PER MINUTE AND LITERS) PER LINEAL FOOT OF SCREEN. Johnson Screens was founded in 1904 by Edward E. Johnson after inventing the world’s first continuous slot wire wrapped well screen. Considered a revolution in technology for the industry, the continuous slot well screen provided more open area per square foot of screen than other conventional methods, allowing more water into the well with more efficiency. Johnson Screens offers a complete.
6-1. Setting Casing. In rotary-drilled water wells, you can set the casing in the borehole after you finish drilling. However, you must set the casing and grout it near the surface. This prevents the upper portion of the borehole from caving in.
For water wells drilled in rock aquifers, you can place the casing through the unconsolidated strata and into the rock to get a tight seal. However, this method does not ensure a tight seal. You can improve the seal by using the following procedures:
NOTE: You cannot pour grout through drilling fluid to properly seal the casing.
6-2. Selecting Casing. Well casing is plastic, wrought iron, alloyed or unalloyed steel, or ingot iron. Well-completion kits have either plastic (Figure 6-1) or steel casing. You must know the properties of other casings because you may have to use them. When selecting the casing, consider the stress factor during the installation process, the corrosive element of the water, and the subsurface formation.
If you use casings other than those in the well-completion kits, you must specify the weight per foot of pipe you want to use. The tables in A100-66, American Water Works Association Standard for Deep Wells (AWWA), present data on the steel and wrought-iron pipes used as permanent well casings. Joints for permanent casings should have threaded couplings or should be welded or cemented so they are watertight from the bottom of the casing to a point above ground. This precaution will prevent contaminated surface water and groundwater from entering the system. Table 6-1 lists hole diameters for various sizes and types of well casings.
6-3. Installing Casing.
a. Open-Hole Method. With this method, install casing using the following procedures:
b. Single-String Method. With this method, you install the casing and screen (that have been joined) in a single assembly. See paragraph 6-6a for installation.
c. Wash-In Method (Jetted Wells). With this method, you advance the borehole for an expedient jetted-well construction. See paragraph 9-2b(1) for installation.
d. Driven Method (Driven Wells). Install the casing as with the borehole, the cable-tool, or driven-point well method. See paragraph 9-3 for installation.
e. Uncased-Interval Method. In rock, you normally leave the lower portion of the borehole uncased because water emerges from irregular functions in the borehole wall. Therefore, for the well to function properly, you must be careful when locating the bottom of the cased portion in relation to any impermeable zone. Once you establish the depth, drill down and set the casing. Then drill a smaller hole to full depth and proceed with development.
6-4. Grouting and Sealing Casing. Once grout is mixed, it starts to set. Therefore, place the mixture immediately after mixing it. You must have freshly mixed grout continuously to meet requirements. Portland cement meets most grouting requirements. (You can use a quick-hardening cement to save time.) For proper consistency, use no more than 6 gallons of water per 94-pound sack of cement. If you need a large amount of grout, add 1 cubic foot of fine or medium sand for each sack of cement. Add a few pounds of bentonite or hydrated lime per sack of cement for a better flow. For small jobs and if no equipment is available, use a 55-gallon steel drum as a mixing tank. Put 20 to 24 gallons of water in the bard and slowly add 4 bags of cement while stirring or jetting the water. Use as many mixing barrels as the job requires. If a concrete mixer is available, mix batches and dump them into a storage vat for future use.
You can force grout into place using pumps or air or water pressure. In some cases, you can place grout using a dump bailer. If you use the tremie methods, you will need one or more strings of pipe with small diameters. Other equipment you may need to place grout are a mixing tank, hoses, and a feed hopper.
a. Dump-Bailer Method. With this method, you can place grout simply and with a minimum amount of equipment. On the dump-bailer, the bottom valve opens and the operator can unload grout at a specified location. This method works best when you need to grout only the lower portion of the casing. Use the following procedures to place grout:
If you anticipate difficulty in filling the casing with water when it is lifted in the borehole, you can add water on top of the grout without lifting the casing. Calculate the volume of grout in the casing. Fill the casing to the top with water. Connect a pump so that you can force in additional water. Pump water into the casing, measuring the volume pumped, until you put in a quantity equal to the volume of grout. This will force all or most of the grout out of the lower end of the casing. You can place a wad of burlap on top of the grout before filling the casing with water to keep the fluids separated.
b. Inside-Tremie Method. With this method, you place the grout in the bottom of the hole through a tremie pipe that is set inside the casing (Figure 6-2). The grout will either descend naturally or you may have to pump it through the pipe. Make sure that the tremie pipe is at least 1 inch in diameter. With this method and any other method where you place the grout inside the casing, make sure that water or drilling fluid circulates up and around the casing before you start grouting. To check this, cap the casing and pump in water. If the water comes to the surface outside the casing, you can start grouting. Use the following procedures to complete the tremie method:
c. Outside-Tremie Method. With this method, you use a tremie pipe to deliver grouting outside the casing. This method is not recommended for depths greater than 100 feet. You can use this method if the space between the casing and the borehole wall is large enough to contain a 1-inch tremie pipe. Use the following procedures to complete grouting using this method:
6-5. Selecting Screens. The military uses continuous-slot screens (Figure 6-4) when drilling wells using the rotary method. You make the screens by winding triangular sections around a skeleton of longitudinal rods. Join the triangular sections and rods securely wherever they cress. The screens are constructed of either PVC or stainless steel and are packed in the well-completion kits. Some important factors to remember when selecting screens are that they--
a. Types.
(1) PVC Screens. These screens must beat least 8 inches in diameter. Continuous-slot PVC screens are in the 600-foot well-completion kits packed in boxes containing four 20-inch-long sections that can be joined together (Figure 6-5). The kits should contain enough sections to assemble up to 50 feet of continuous-slot, 8-inch well screen.
You can use the PVC casings to construct an alternative screen. You saw or mill horizontal slots in sections of the 20-foot-long casing. You cut six rows of slots down the casing. The slots are 1/2 inch apart at a width of 0.025 inch. You can construct PVC screens in the field by cutting slots in PVC casing with saws. The following lists saws and approximate slot sizes:
These makeshift screens are not as efficient as the continuous-slot screens because of the relatively low open area per foot of screen. However, you should use these screens when the kit contains an insufficient number of continuous-slot screens. The alternative screens are the same as the casing sections. You can place the screens intermittently up the well if you screen more than one aquifer or waterbearing strata. If you screen multiple intervals, you must place gravel packs around the screens and backfilling between the screens. If sufficient gravel-pack material is available, use it continuously to above the top of the screen.
(2) Stainless-Steel Screens. These screens are usually 6 inches in diameter and come in 10- and 20-foot sections. You can join the sections to make longer pieces. Most stocked screens have 0.025-inch openings that are suitable for medium-sand formations. Screens with other slot openings are available and may be needed for special installations. Various end fittings are available so you can use different installation methods. See paragraphs 6-6a through d for uses of these end fittings.
(3) Pipe-Base screen. You make this screen by wrapping a trapezoidal-shaped wire around a pipe base that has drilling holes evenly spaced. A pipe-base screen is strong and suitable for deep wells. The screen has two sets of openings. Outer openings are between adjacent turns of the wrapping wire and inner openings are the holes drilled in the pipe base. The percentage of open area per foot of screen (usually low) governs the efficiency of the screen. These screens come in 3- and 4-inch pipe bases for field operations.
b. Lengths. Use the electric logging units in the well-completion kits to determine the location, depth, and thickness of an aquifer. Screen length should not exceed the thickness of thin aquifers. You should screen the bottom third of unconfined aquifers and 75 to 80 percent of confined aquifers. However, for interlayered fine and coarse beds, consider the thickness of the coarse strata when determining screen length. Set the screen in the coarse strata. If you have a choice of slot sizes, consider the percentage of the open area or intake area of the well screen to determine length. Use the following calculations to determine the amount of screen to use during drilling operations:
(1) Surface Area.
SA = p (OD)(12)
where--
SA = surface area, in inches per foot.
OD = outside diameter of the screen, in inches.
(2) Open Area.
where--
OA = open area as a percentage.
SO = slot opening, in inches.
WD = wire diameter, in inches.
(3) Total Area.
TA = (SA)(OA)
where--
TA = total area, in square inches.
SA = surface area, in inches per foot.
OA = open area, as a percentage.
(4) Transmitting Capacity.
TC = (TA).31
where--
TC = transmitting capacity, in GPM per foot of screen (based on one-tenth foot per minute of velocity).
TA = total area, in square inches.
(5) Screen Length.
where--
SL = screen length required, in linear feet.
PR = pumping requirement, in GPM.
TC = transmitting capacity, in GPM
The following example uses the above equations to determine the amount of 12-inch screen required at one-tenth foot per minute of velocity with a slot opening of 0.040 inch, a wire size of 0.092 inch, and a pumping requirement of 800 GPM:
c. Diameters. The diameter of the well screen usually corresponds to the diameter of the well casing. If you are considering alternative diameters, consider the following:
d. Slot Sizes. You should understand the function of slot size in well construction. When possible, choose the screen slot size to fit the gradation or grain sizes of the aquifer. Sand and gravel interaction greatly affects the development of the formation around the screen. Small openings limit well yield. Also, small slot sizes produce high velocity in the water passing through the screen. In time, scale or incrustation tends to form on the screen. If the openings are too large, you may have to develop the well more than usual, or you may not be able to clear the well of sand.
Screen slots that are sized to retain the coarsest one-third to one-half of sand or gravel of the aquifer work best in a naturally developed well. About two-thirds of the sand in the layer behind the screen should pass through the slots. A screen set across both coarse and fine strata may need sections with different slot sizes. If you have to pack the screen with gravel artificially, make sure the slot openings correspond to the size of the gravel you use. Screen openings that retain about nine tenths of the gravel work best.
6-6. Installing Screen. You can use several methods to install screens in rotary-drilled wells. To set well screens, you will use the screen hook and casing elevators. You use the hook to engage a bail in the bottom of the screen to suspend the screen on either the sand line or hoist line while lowering the screen into the well (Figure 6-6). Do not pull the screen with the hook after the formation has closed in around the screen. If you are installing a screen using the telescoping method and you must seal the casing, you will need rubber or neoprene packers. All screen-setting methods require accurate and complete measurements of pipe, screen, cable length, and hole depth.
a. Single-String Method. With this method, you install the casing and screen as one assembly. Figure 6-7 shows a single-string assembly equipped with fittings for the washdown method. You can omit the washdown fittings if the hole stays open at the bottom. Use the following procedures to install the assembly:
For deep wells and wells requiring surface casing, you can use the following modified telescoping procedure:
A disadvantage of the single-string method is the weight of a long string of casing on top of the screen. When the screen touches bottom, it becomes a loaded column that can easily buckle because of its slenderness. When the screen reaches the correct depth, you can prevent buckling by supporting the screen on casing elevators until the formation material collapses around the screen and supports it laterally.
b. Pull-Back Method. This is another method of installing a telescoping screen. Use the following procedures for this method:
c. Open-Hole Method. Use this method to install telescoping screen when the depth and thickness of the aquifer have been predetermined. Use the following procedures for this method:
Use the closed bail plug and the packer top-end fittings to support the screen and sand trap (Figure 6-8). With this method, the diameter of the screen must be smaller than the casing, since the hole drilled for the screen will be no larger than the inside diameter of the casing. Also, make sure that the packer fitting at the top of the screen is the proper size to seal inside the casing. The drilling mud must be heavy and thick to prevent the open borehole from caving in, and the mud must be completely removed from the aquifer during development.
d. Washdown Method. This method works best if the aquifer is composed of fine to coarse sand with little or no gravel. The screen fittings you need for this method are a washdown or self-closing bottom. Figure 6-9 shows a fitting you can use when using a telescoping method to set the screen through the casing. Set the casing from the surface to slightly below the depth where you will install the top of the screen. Screw a section of wash pipe into the left-hand female thread of the self-closing bottom and attach the bottom to the screen or sand trap with the wash pipe projecting through the screen. Lift the entire assembly by the wash pipe and lower the screen inside the casing. Add sections of wash pipe until the bottom of the screen is near the lower end of the casing.
Use the following procedures for the washdown method:
e. Bail-Down Method. With this method, you need special end fittings for the screen. Figure 6-10 shows an assembled bail-down shoe in the bottom of the screen. The bail-down shoe has a special nipple that has right-and left-hand threads and a coupling with right-and left-hand threads. Figure 6-11 shows a shoe with a guide pipe that extends below the screen.
Use the following procedures for the bail-down operation:
If you use a different type of bail-down shoe, the left-hand threaded connection for the bailing pipe may be in the opening in the shoe or it may be in the packer fitting at the top of the screen. In either case, use the same procedures as above for operating the bailing down, plugging the bottom, and removing the bailing pipe.
Under certain conditions, you can bail down a well screen without using a bail-down shoe. The bailing pipe is not connected to the screen. You fit the pipe's lower end with a flange or coupling large enough to press on the packer at the top of the screen. The weight of the bailing pipe rests on the screen. You fit the lower end of the screen with an open ring or a short piece of pipe. Be very careful when using this method because the screen is not connected to the bailing pipe and you cannot control the screen's movement from the surface. Careful measurements will prevent sinking the screen too far. This method should be limited to fairly short screens. Plug the bottom of the screen by putting a small bag of dry concrete mix in the bottom and tapping the concrete lightly with the drill bit or other tool.
6-7. Placing Gravel. The most important criteria for grovel pack (artificial sand filters) are correct grain sizes and screen slot opening. Grading should be in proper relation to the grading of the sand in the aquifer. You could have trouble if you use gravel that is too coarse. Coarse, uniformly graded filter sand (about 1/8 inch) makes the best gravel pack for most fine-sand aquifers. You should use fine gravel (1/4-inch maximum size) to pack aquifers consisting of medium or coarse sand. Use a screen with openings that cover about 90 percent of the gravel pack. The following is a field method for producing a filter material or gravel pack from a sand and gravel deposit for a medium sand aquifer.
NOTE: A layer of hardware cloth under the screen provides extra strength to the sieve.
a. Open-Hole Placement. Where drilling mud keeps the borehole open, you can install a gravel pack using the positive-placement method. This method is the most common and best suited to military field operations. Use the following procedures for this placement method:
NOTE: Basket-type centering guides work best.
Development work must be thorough when you drill the borehole using the rotary method because the mud cake on the borehole wall is sandwiched between the gravel pack and the face of the formation. You must break up the mud cake and bring it up through the gravel into the well. Any mud cake not removed reduces the efficiency and yield of the completed well. To ensure that you remove all of the mud cake, limit the thickness of the gravel envelope around the screen to a few inches. A common mistake is to drill a very large borehole and use a small screen, making the gravel too thick for satisfactory results.
Another common mistake is to try and place gravel pack into a small annular space, such as 1 inch. The gravel pack usually bridges at a coupling and does not get down around the well screen. A 2-inch annular space is minimum; 3- to 5-inch spaces are best. Remember, the annular space is the difference between the outside of the casing and the wall of the borehole with the casing centered in the hole. In most cases, you must also consider the outside diameter of the couplings.
b. Tremie Placement. You can use a tremie pipe when placing gravel-pack materials. The fine and course particles should not separate, as in the open-hole placement, when the aggregate settles through the drilling fluid in the well. Lower a string of 2-inch (or larger) pipe into the annular space between the inner and outer casings. Feed the gravel into the hopper at the top of the pipe. Feed water into the pipe with the gravel to avoid bridging the material in the pipe. The pipe raises as the gravel builds up around the well screen. The tremie system is practical for placing the gravel pack in shallow to moderately deep wells.
c. Bail-Down Placement. With this method, you can place a gravel pack as you install the screen. Feed the grovel around the screen, it will go downward with the screen. The bail-down shoe used is somewhat larger than the screen so that gravel being added will follow down and around as the screen sinks in the formation. Figure 6-12 shows this operation. Development work is an essential part of this method. Screen openings must be larger than the grain size of the aquifer so enough aquifer sand will pass through and the gravel pack will replace the sand around the screen.
d. Double-Casing Placement. With this method, you place gravel and use a temporary outer casing (Figure 6-13). With this method, you pull back the casing as you pour gravel into the space. This method is somewhat similar to pull-back screen installation.
6-8. Using Alternative Methods.
a. Formation Stabilizer. When you do not use a grovel pack you can place formation-stabilizer material to help prevent deterioration of the annular space outside the screen. Fine, loose strata may cave into that space, enter the screened interval, and degrade the well. The decision to use this material usually occurs during the well-construction process. In unstable formations, consider stabilizing wherever the annular space is more than 2 inches thick.
Grain size is important since you will develop the aquifer naturally, and as much as half of the stabilizing material could flow through the screen. The grain size should average slightly coarser than that of the aquifer and should be well distributed. Widely used formation stabilize are concrete or mortar sand. Use the following procedures when placing formation stabilizers:
b. Unscreened Well. In competent rock, you usually tap the aquifer through numerous, irregularly spaced fractures. Once cleared of mud and rock fragments, the fracture stay open and the intake interval functions efficiently for a longtime. You should not need a screen in such a rock well. If you anticipate an unscreened-well design, you must be particularly attentive to the location of the top of the unscreened intake interval and its relation to the position and thickness of any impermeable layer.
Join the GlobalSecurity.org mailing list |
The Science of Slotted PVC/HDPE screen.
Hello, I need some slotted screen for my well. Can you help me? This is sometimes a common question and all the information we get to work with. The truth and science behind this scenario can be overwhelming, but by asking a few more questions we can offer the exact product for your specific job.
Lets start with the raw material. There are several plastics used throughout the world for water wells. The type of well you have has a lot to do with which material is used. In addition, the type of well installation may change your request for the raw material.
PVC, CPVC and HDPE are the most common materials used today. Whether you are sleaving an existing well, installing a new monitoring well or drilling a leachate collection system, one of these materials will surly be asked for.
There are 2 basic requirements for these products.
The casing. The casing is the pipe itself. It is available in a few basic configurations. The most widely available is belled end or solvent weld. One end of the pipe is extruded so that the belled end slips over the plain end and can be glued together with PVC cement. This works well for horizontal applications but is not very strong for deep vertical wells. The ASTM F-480 thread is another option. This is a flush joint thread which has a square thread machined directly on each end of the pipe utilizing the wall thickness of the pipe to accommodate the thread. The big advantage of this thread is that the joint is “flush”. There is no joint to catch on going down the hole or for tooling to snag while inside of the pipe. “NPT” of National Pipe thread is one more option, but requires a threaded coupler to join the pipe together.
The Screen. Slotting the raw PVC material is usually an easy task. Typically, a machine will have an arbor loaded with slitting saw blades and the machine will travel lengthwise along the pipe slotting as it goes. Farwest Special Products in Edgewood, WA has six of these machines, 2 of which are CNC controlled. “We are able to slot just about any configuration, in just about any size of pipe from ¼” through 24” diameters” says Dave Baca from Farwest. Dave has been with the company, formerly known as Aardvark Corporation for 17 years, and has seen just about every slotting configuration possible. The biggest concern when it comes to knowing what to order will be the amount of open area. Open area is calculated in the following manner.
Multiply the slot width x the slot length (inside of pipe) x number of slots /row/ft x number of rows around the diameter. The spacing of the slots and the slot width will determine the number of slots /row/ft. For example.
.020” slot width x 1.0” slot length x 42 slots/row/ft x 6 = 5.04 sq. In / ft of screen.
This dimension is based on 4” schedule 40 PVC pipe with a minimum I.D. slot length of 1.0 inches and ¼” spacing between the slots.
Using these numbers of open area, we can then multiply the amount of open area / ft to .3117 and have what is called intake velocity per foot of screen. The answer from the above formula, 5.04 x .3117 = 1.5709 G.P.M. per foot of screen. You can then take that out to a 10 foot length of pipe and so on. This information will be very helpful because of two major concerns. The first is the size of soils you are trying to keep out of the screen. In fine sands a slot width of .060” will allow that material smaller than .060” to come into the screen, eventually blocking the screen. The .020” wide slots will keep most of the fine sands out of the screen yet allowing the water to pass through the slots without bridging.
The second concern to look at is the production of the well. The “science” or better described; magic of determining the size of screen is combining the soil size and the well production to allow the most amount of water into the well and screening out the soil. A Hydrologist will perform most of this work if one is hired for the site work. If not, you will need to look at your drill cuttings while you are drilling and make that determination where you find the water.
The production of your well can be made adequate or diminished based on the size and type of screen used. These basic steps should help you choose the correct PVC screen for each job.
Once this data is available the pipe can be slotted and threads machined on the pipe and shipped worldwide to your jobsite. As slotted PVC and HDPE have several market fields, many construction companies are also switching to slotted pipe versus perforated pipe for their drainage needs. Slotted screens have approximately 60 percent more open area per foot than conventional perforated pipe. There is also less chance for bridging, which can cut down the intake velocity.
Joints: Joining the casing and screen will be another important issue to think about. After all, if you buy a screen made from 4” schedule 40 PVC with a belled end, how will you join that to the 4” schedule 40 ASTM F-480 PVC casing ?
Typically, when installing monitoring wells, there are 4 basic parts when talking about the pipe. Starting at the bottom, they are…
1.Bottom plug or End plug: This is usually a 6” long length of PVC pipe with a female flush joint thread on one end, and a cap machined on the other end.
2.The PVC screen, which also has the flush joint threads, would screw into the bottom plug. The screen length will be determined by the driller depending on where the water is.
3.Attached to the screen is the flush joint casing. The casing would then be installed to the surface.
4.The last part of the well is a locking well cap. These are made from steel or PVC and have a rubber gasket to seal any objects from entering the well as well as a locking device to prevent vandalism.
ASTM F-480: This is a standard in ASTM, which relates specifically to the threads on plastic pipe as well as metal pipe. First introduced to ASTM by Aardvark Corporation (now Farwest Special Products) in 1972 and was developed as a fast connecting yet strong thread for horizontal water well drilling. After several thousand dollars of testing, it was introduced to ASTM where they performed some of their own testing and made it a standard. Today, The F-480 thread is used world wide in a multitude of applications from monitoring wells, piezometers, edge drains and dewatering wells.
The biggest advantage of the F-480 threads is the fact that there is no ridge or lip when the joints are screwed together. The outside diameter and the inside diameters are flush with each other.
Another distinct advantage is the tensile strength of the thread. In a vertical application, such as a monitoring well, 2” schedule 40 PVC with ASTM F-480 threads will hang 1400 lbs. If you calculate the weight of the pipe itself at .689 lbs/ft, you are able to install 2000 feet of pipe with a .2 percent safety factor.
In a study by the United States Department of the Interior in July of 1989 publication (R-89-06) by Jay Swihart, the Applied Sciences Branch concluded the following summary.
“ The research results confirm that PVC casing and well screen are highly suitable for many well applications and that strengths of most components are adequate for deeper installations than originally considered. The results also show that the collapse strength of most components can be accurately predicted by simple stiffness tests; however, there are still concerns about collapse at elevated grouting temperatures that were not addressed. Shortcomings of PVC well components include low pressure ratings of flush threaded joints and low tensile strengths for some joint systems. These problems should be investigated further.”
These issues were investigated further and the result was the introduction of the o-ring seal at the base of the male thread. The afore mentioned study by the Department of the Interior went on to state “ASTM recently approved a threaded joint standard (ASTM: F-480) which requires an O-ring gasket. This standard along with computerized machining operations currently being perfected by the manufacturers should improve the watertightness of these threaded joints.”
The main reason for the ASTM Standard (ASTM F-480) is compatibility. How many of you have ordered flush joint pipe from two vendors and found that they do not match up or thread together. This is an issue that continues to haunt us even today. I have found that you should ask for ASTM F-480 threads if you need to have all of the joints mate up. Some manufacturers of threaded casing and screen are advertising, “flush joint pipe”, and that is exactly what you will receive. There is likely no testing or data provided for these joints. Do you really want to fish out 200 meters of pipe due to a faulty joint? ASTM and their standards are known world wide and used worldwide. The compatibility and versatility depends on your choice of the type of products you order. The correct choice will cause fewer headaches in your planning and scheduling.
Contributed by:
Dave Baca
Farwest Aircraft - Special Products Division
800-438-3808
dave-b@farwestair.com
www.farwestair.com/products